Holbrook Avenue Reconstruction

The Holbrook Avenue Reconstruction Roadway and Water Main Project presented numerous challenges, requiring extensive knowledge of Wayne County and its existing infrastructure.

Among the challenges, most homes required in-street parking along the roadway where construction took place. Complicating matters further, a senior living plaza and a commercial building needing continuous access were located on the site. Extra caution was also needed due to a building abutting the existing right-of-way.

In addition, the presence of an old pedestrian tunnel underneath the roadway required excessive caution to remove and install new utilities properly.

Civil Engineering Civil Engineering

Land Surveying Land Surveying

Construction Engineering Construction Engineering

Key Facts
  • A commercial building and senior living plaza needed to remain accessible throughout construction
  • Another building abutting existing right of way created a limited workspace, requiring extra caution
  • Residential street parking presented additional challenges
  • "Project of the Year 2020" by American Public Works Association, Downriver Branch & "Project of the Year 2021" by Michigan Concrete Association
Client

City of Hamtramck

Location

Holbrook Avenue from Lumpkin Street to Joseph Campau Street

Project Date

October 2020

Project Costs

$2,200,000